Travel Advisory

April 19, 2024

At the Rumson work siteTuesday 9/5 – Friday 9/87 a.m. to 5:30 p.m.
At the Seabright work siteTuesday 9/5 – Friday 9/87 a.m. to 7:30 p.m.

Bridge replacement activity is scheduled from 7 a.m. to 3:30 p.m., weather permitting, for Monday, April 22 through Friday, April 26.

Roadway and Sidewalk Information

  • The south side (eastbound) sidewalk of the bridge is closed.
  • All roadway and sidewalk travelers should be aware of construction and delivery vehicles entering and exiting the work areas on both sides of Rumson Road (CR 520) in Rumson and on the southbound side of Ocean Avenue (Route 36) in Sea Bright.
  • Temporary delays are possible on any Contractor work day due to movement of construction vehicles and equipment.

Waterway Information

  • For channel closure information, please click here.
  • Bridge replacement work activity continues on both sides of the Shrewsbury River south of the bridge.

Please visit this page regularly for updates.

Thank you for your continued support and understanding during the construction phase of this important bridge replacement project.


Local Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation

Recent News