Night Work and Travel Delays Anticipated on Monday, March 6, 2023

The Contractor is scheduled to pour bridge pier concrete footing on or about Monday, March 6, 2023, weather permitting.

  • The Contractor will begin work at 4 a.m. and continue until 11 p.m.
  • Concrete trucks will be entering and exiting the Sea Bright construction area on Route 36/Ocean Avenue frequently between 6 a.m. and 5 p.m. The trucks may be queued in the northbound shoulder of Route 36. Sea Bright Police will assist with traffic control.
  • If necessary, such as an emergency, the Contractor may close the southeast shoulder on the bridge (CR 520).

Please allow extra travel time on Monday, March 6 between 4 a.m. and 11 p.m.

The Project Team appreciates your continued support and understanding during the construction phase of this important bridge replacement project.