Recent News

U.S. Coast Guard Issues Notice of Proposed Rulemaking

On May 23, 2023, the U.S. Coast Guard (USCG) issued a Notice of Proposed Rulemaking to establish a temporary safety zone on the Shrewsbury River from September 25, 2023 through December 31, 2024. Please see the attachment for details. Comments on the proposal must be submitted by June 22, 2023 through… Read more »

Shrewsbury River Full and Half Channel Closures

Due to bridge replacement construction activity in the Shrewsbury River, the navigational channel width is currently reduced from 75′ to 65′. Signs are posted for mariners. In the future, there will be full and half channel closures for installation of the new bridge spans.  Please see the Public Notice with… Read more »

Shrewsbury River Temporary Channel Width Reduction in Effect

Due to bridge replacement construction activity in the Shrewsbury River, the navigational channel width is reduced from 75′ to 65′. Signs are posted for mariners. Please click here to see the Public Notice. Any other impacts to river and roadway traffic due to construction activity will continue to be posted… Read more »

Update on Shrewsbury River Temporary Channel Width Reduction

The temporary channel width reduction previously noted for late summer is now anticipated in the Fall of 2022. Notice had been given in May that bridge replacement construction activity in the Shrewsbury River will require the existing navigational channel width be reduced from 75′ to 65′ for an estimated 12… Read more »

Shrewsbury River Temporary Channel Width Reduction

On or about July 30, 2022, weather permitting, bridge replacement construction activity in the Shrewsbury River will require the existing navigational channel width to be reduced from 75′ to 65′ for an estimated 12 months. The channel will continue to be open to mariners. For additional details, click to view… Read more »

Local Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation