on Rumson Road (CR520) over Shrewsbury River
Borough of Rumson and Borough of Sea Bright, New Jersey
Rumson-Sea Bright Bridge S-32 Project
on Rumson Road (CR520) over Shrewsbury River
MONMOUTH COUNTY
Rumson-Sea Bright Bridge S-32 Project
on Rumson Road (CR520) over Shrewsbury River
Borough of Rumson and Borough of Sea Bright, New Jersey
Rumson-Sea Bright Bridge S-32 Project
on Rumson Road (CR520) over Shrewsbury River
The eastern side of the navigational channel under the bridge remains open for marine travel: Dates are subject to change based on weather conditions and production factors. Any schedule changes or impacts to river and roadway traffic will continue to be posted to the Travel Advisory page of this website. The US Coast Guard (USCG) approved the…
The eastern side of the navigational channel under the bridge remains open for marine travel with the following conditions: Dates are subject to change based on weather conditions and production factors. Any schedule changes or impacts to river and roadway traffic will continue to be posted to the Travel Advisory page of this website. The US Coast…
The reconfigured access to Old Rumson Road has been monitored since June 2024. Monmouth County engineers have developed a revised plan for the Rumson Road intersections with Ward Avenue/South Ward Avenue and with Old Rumson Road. The Borough of Rumson and Monmouth County engineers will be holding a meeting to present the revised plan: Date:…
As of 6 a.m. on Wednesday, November 20, it is anticipated that the channel below the Rumson-Sea Bright Bridge will be open at half width (37.5 feet) with the eastern half available for marine travel. Dates are subject to change based on weather conditions and production factors. Any schedule changes or impacts to river and…
There will be no bridge openings from 8 a.m. to 10 a.m. on Wednesday, November 13 due to necessary construction activity on the new bridge spans. After 7 p.m. on November 14 until 6 a.m. on November 18, the channel is scheduled to be open at full width (75 feet). As of 6 a.m. on…
After 7:00 p.m. on Friday, October 25, the western half of the channel under the bridge is scheduled to be open for marine travel. Dates are subject to change based on weather conditions and production factors. Any schedule changes or impacts to river and roadway traffic will continue to be posted to the Travel Advisory page of…
As of 6:00 a.m. on Monday, October 21, 2024 until 7:00 p.m. on Friday, October 25, 2024, the channel will be CLOSED to all marine travel. There will be no bridge openings. After 7:00 p.m. on Friday, October 25, the channel is scheduled to be open at half width (37.5 feet) until 7 p.m. on…
The Shrewsbury River navigational channel under the Rumson-Sea Bright Bridge is scheduled to be open at the full width of 75 feet with no restrictions after 4:00 p.m. on Friday, October 11, 2024. The full width will be available to marine traffic until Monday, October 21, 2024. As of 6:00 a.m. on Monday, October 21,…
The Shrewsbury River navigational channel width under the bridge will be open to 37.5 feet due to construction of the new bridge. The channel will remain at this half width from Friday, September 20, 2024 through Friday, October 25, 2024. During this timeframe, passage for marine vessels under the Rumson-Sea Bright Bridge will be available…
The US Coast Guard (USCG) approved the Fall 2024-Spring 2025 schedule for full and half channel closures necessary for installation of the new bridge spans.