Local Concept Development (LCD) Phase

MeetingsDate/Time/LocationPurpose
Local Officials Meeting No. 1 with RumsonJanuary 24, 2012
9:00 a.m.
Rumson Municipal Building
– Introduce the project team
– Present project status and schedule
– Obtain input on community interests associated with County Bridge S-32
Local Officials Meeting No. 1 with Sea BrightJanuary 30, 2012
9:00a.m.
Sea Bright Municipal Building
Community Stakeholder Meeting (CSM) No. 1February 15, 2012
10:00 a.m.
Rumson Municipal Building
– Introduce the project team
– Present project status and schedule
– Obtain input on community interests associated with County Bridge S-32
Public Information Center (PIC) No. 1February 27, 2012
1:00-4:00 p.m.
Sea Bright Municipal Building
and
6:00-9:00 p.m.
Rumson Municipal Building
– Introduce the project team
– Present project status and schedule
– Obtain input from the general public regarding community issues and interests associated with County Bridge S-32
Community Stakeholder Meeting No. 2June 26, 2012
1:00-3:00 p.m.
Holy Cross School, Rumson
– Review project status
– Present Purpose and Need Statement
– Discuss conceptual alternatives for proposed improvements to County Bridge S-32
Local Officials Meeting No. 2 with Sea Bright and RumsonOctober 4, 2012
9:30 a.m.
Rumson Municipal Building
– Present project status and schedule
– Review Alternatives Comparison Matrix
– Prepare for PIC meetings
Public Information Center (PIC) No. 2January 23, 2013
2:00-4:00 p.m.
Sea Bright Municipal Building
and
6:00 p.m. – 8:00 p.m.
Rumson-Fair Haven High School, Rumson
– Inform the public of the conceptual alternatives
– Solicit public input and comment on the proposed Preliminary Preferred Alternative (PPA)
Local Officials Meeting No. 3 with RumsonJanuary 30, 2013
4:30 p.m.
Rumson Municipal Building
– Present project status and schedule
– Discuss PIC meetings, PPA, and next steps
Local Officials Meeting No. 3 with Sea BrightFebruary 4, 2013
9:00 a.m.
Sea Bright Municipal Building
Local Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation

Recent News