County of Monmouth Seal

MONMOUTH COUNTY

Rumson-Sea Bright Bridge S-32 Project

on Rumson Road (CR520) over Shrewsbury River

Borough of Rumson and Borough of Sea Bright, New Jersey

Rumson-Sea Bright Bridge S-32 Project

on Rumson Road (CR520) over Shrewsbury River

Travel Advisory

April 25, 2025

Bridge replacement activity is planned from 7 a.m. to 3:30 p.m. for Saturday 4/26 and from 7 a.m. to 5 p.m. Monday 4/28/25 through Saturday 5/3, weather permitting. Scheduled construction activities are listed below the travel advisory information.

Waterway Information – NEW INFORMATION AS OF 4/25/25

  • 4/25/25 – 5/1/25 – NO BRIDGE OPENINGS
    The western half of the channel under the bridge is scheduled to be open for marine travel with horizontal clearance of 37.5 feet and vertical clearance of 15 feet at Mean High Water (MHW)/18.5 feet at Mean Low Water (MLW).
  • 5/1/25 – 5/8/25 – NO BRIDGE OPENINGS
    The channel is  scheduled to be fully open for marine travel with horizontal clearance of 75 feet and vertical clearance of 15 feet at MHW/18.5 feet at MLW.
  • 5/8/25 – 5/22/25 – HALF CHANNEL BRIDGE OPENINGS
    One span, either east or west, will be in the down position on an as-needed basis, and the opposite half of the channel will be open with horizontal clearance of 37.5 feet and no vertical restriction.
  • The United States Coast Guard (USCG) has jurisdiction over the navigational channel. USCG has granted permission for the partial closures of the channel and for the temporary deviation from normal drawbridge operations. Monmouth County must comply with the dates approved by the USCG.
  • Dates and times are subject to change based on weather conditions and production factors.

Roadway and Sidewalk Information

  • Please be aware of traffic pattern changes and possible travel delays in Sea Bright at the intersection of Route 36 (Ocean Ave) and Rumson Road (CR 520).
  • All roadway and sidewalk travelers should be aware of construction and delivery vehicles entering and exiting the work areas on both sides of Rumson Road in Rumson and on the southbound side of Route 36 in Sea Bright.
  • Temporary delays are possible on any Contractor workday due to movement of construction vehicles and equipment.
  • The south side (eastbound) sidewalk of the bridge is closed.

Scheduled Construction Activities

Rumson

  • Form, Reinforce and Pour Span 4 Deck
  • Install Interior Finishes at Control House
  • Install Span lock and Machining
  • Install Receptacles, Lighting, Tap Boxes, CCTV & Exterior Lighting

 Seabright

  • Install Interior Finishes at Gatekeeper House
  • Form, Reinforce and Pour Span 6
  • Form, Reinforce and Pour SE Retaining Wall Stem
  • Install Span 6 Steel
  • Install Metal Panels for Machinery Enclosure
  • Seed and Install Plantings Along Rt 36 East Curb
  • Install Span lock and Machining
  • Install Trunion and Align Machinery
  • Install MCCs, Drive Cabinets, PLC Cabinets

Please visit this page regularly for updates.

Thank you for your continued support and understanding during the construction phase of this important bridge replacement project.

Local Project Delivery Process

Purpose & Need Statement

Data Collection & Environmental Screening Report

Selection of Preliminary Preferred Alternative

Concept Development Report

NEPA Classification

Create Design Communications Report

Initial Public Outreach & Involvement

Approved Design Exception Report

Cost Estimates (Final Design, ROW & Construction)

Approved Environmental Document

Approved Project Plan

Preliminary Engineering Report

Update Design Communications Report

Continued Public Outreach & Involvement

Construction Contract Documents & PS&E Package

Environmental Reevaluations

Environmental Permits

Acquisition of ROW

Update Design Communications Report

Continued Public Outreach & Involvement

Implement and Complete Construction

Continue Public Outreach

As-Builts

Update and Finalize Design Communications Report

Close-out Documentation

Recent News