The current schedule for bridge openings is as follows:
5 p.m. Friday 6/6 to 7 a.m. Monday 6/9 | Full channel open for marine traffic |
Monday 6/9 through Thursday 6/12, 7 a.m.-5 p.m. | Single span lifts will be on signal Two span lifts require 2 hours advance notice |
Dates and times are subject to change based on weather conditions and production factors.
The United States Coast Guard (USCG) has jurisdiction over the navigational channel. USCG has granted permission for the partial closures of the channel and for the temporary deviation from normal drawbridge operations. Monmouth County must comply with the dates approved by the USCG.
To access the USCG’s Local Notice to Mariners, go to Useful Links.
If you have questions or comments, please Contact Us.
The Project Team appreciates your continued support and understanding during the construction phase of this important bridge replacement.