The US Coast Guard (USCG) approved the Fall 2024-Spring 2025 schedule for full and half channel closures necessary for installation of the new bridge spans. Start and end times have been updated for the September-October dates:
Start Date | End Date | |
---|---|---|
FULL CLOSURE No bridge openings No marine traffic | September 16, 2024, 6:00 A.M. | September 20, 2024, 7:00 P.M. |
PARTIAL CLOSURE East half open 37.5’ channel width, west half closed | September 23, 2024, 6:00 A.M. | October 25, 2024, 7:00 P.M. |
The channel under the bridge will be open at full width (75 feet) on the weekends listed below:
Please see the Updated Public Notice (9/13/24) for all full and half closure dates.
Dates are subject to change based on weather conditions and production factors.
Any schedule changes or impacts to river and roadway traffic will continue to be posted to the Travel Advisory page of this website.
To access the USCG’s Local Notice to Mariners, go to Useful Links.
If you have questions or comments, please Contact Us.
The Project Team appreciates your continued support and understanding during the construction phase of this important bridge replacement.